Contract SFS-DEV-004
Overview
The goal of the CLIO Simplification Implementation contract is the implementation in the Lustre source code of the CLIO Simplification Design that resulted from Project 2 of Contract SFS-DEV-003.
For the contract statement of work, see SFS-DEV-004_SOW.pdf
Key People
OpenSFS
- Galen Shipman - OpenSFS Contract Administrator
- Christopher Morrone - OpenSFS Technical Representative
Project Approval Committee (PAC)
- Christopher Morrone - PAC Chair
- Colin Faber
- Patrick Farrell
- Jason Hill
- James Simmons
- Cory Spitz
Intel
- Andreas Dilger - Consulting Architect
- Jinshan Xiong - Lead Engineer
Important Dates
| Milestone task | Elapsed time (weeks) | Expected completion | Forecast completion |
|---|---|---|---|
| Implementation | 15 | start + 15 weeks | Jan 26th 2015 |
| Test and fix | 10 | start + 25 weeks | Apr 6th 2015 |
| Demonstration | 4 | start + 29 weeks | May 4th 2015 |
| Landing | 4 | start + 33 weeks | Jun 1st 2015 |