Contract SFS-DEV-001
Jump to navigation
Jump to search
SFS-DEV-001
Project Status
The table below shows the completion dates of the different phases of the OpenSFS SFS-DEV-001 contract with Intel HPDD. Hyperlinks will lead to the document for each milestone. We will update the table as Intel completes new milestones for each project.
Scope Statement | Solution Architecture | High-level Design | Demonstration | Delivery | Landing | ||
---|---|---|---|---|---|---|---|
MDS Performance | PDIR Ops | 2011-09-28 | 2011-10-12 | 2011-11-09 | 2012-03-19 | 2012-04-30 | 2.2 |
SMP Node Affinity | 2012-03-09 | 2012-04-04 | 2012-05-02 | 2012-10-07 | 2012-12-12 | 2.3 | |
Distributed Name Space (DNE) |
Remote Directories | 2011-10-19 | 2011-12-23 | 2012-02-06 | in progress | in progress | 2.4 |
Striped Directories | in progress | ||||||
Lustre File System Check (LFSCK) |
OI Scrub | 2011-10-05 | 2011-11-03 | n/a | 2012-06-06 | 2012-12-07 | 2.4 |
Fid-in-dirent & lineEA consistency | 2012-10-31 | 2012-11-20 | 2012-12-12 | in progress | in progress | 2.4 | |
MDT-OST Consistency | in progress | ||||||
MDT-MDT Consistency | in progress | ||||||
Performance |