2015-07-06 Protocols Document meeting minutes: Difference between revisions

From OpenSFS Wiki
Jump to navigation Jump to search
Line 18: Line 18:
* remove implementation (Andreas)
* remove implementation (Andreas)
* doc re-orginsation.
* doc re-orginsation.
* state machine for file open or connect.. more effort for connect, but it is better understood by andrew.


=== Milestones to project close ===
=== Milestones to project close ===

Revision as of 12:36, 6 July 2015


Attendees

  • Richard Henwood (Intel)
  • Colin Faber (Seagate)
  • Andrew Uselton (Intel)
  • Chris Horn (Cray)
  • Chris Morrone (LLNL)
  • Andreas Dilger (Intel)
  • Doug Oucharek (Intel)

Agenda

Last Monday, June 29th, OpenSFS notified Intel that it is canceling contract SFS-DEV-005 (the protocol documentation project). Per the contract, cancellation requires 30 days notice. The official end date of the contract was therefore agreed to be July 29th.

Agreed project close goals

  • remove implementation (Andreas)
  • doc re-orginsation.

Milestones to project close

  • next week: implementation removed, re-org begins.
  • week after: re-org complete.
  • final week: final snapshot and lessons learned.

NOTE after 29th July: for the foreseeable future we anticipate the git repo and build infrastructure to be maintained for this project.