Contract SFS-DEV-004
Jump to navigation
Jump to search
Overview
The goal of the CLIO Simplification Implementation contract is the implementation in the Lustre source code of the CLIO Simplification Design that resulted from Project 2 of Contract SFS-DEV-003.
For the contract statement of work, see SFS-DEV-004_SOW.pdf
Key People
OpenSFS
- Galen Shipman - OpenSFS Contract Administrator
- Christopher Morrone - OpenSFS Technical Representative
Project Approval Committee (PAC)
- Christopher Morrone - PAC Chair
- Colin Faber
- Patrick Farrell
- Jason Hill
- James Simmons
- Cory Spitz
Intel
- Andreas Dilger - Consulting Architect
- Jinshan Xiong - Lead Engineer
Important Dates
Milestone task | Elapsed time (weeks) | Expected completion | Forecast completion |
---|---|---|---|
Implementation | 15 | start + 15 weeks | Jan 26th 2015 |
Test and fix | 10 | start + 25 weeks | Apr 6th 2015 |
Demonstration | 4 | start + 29 weeks | May 4th 2015 |
Landing | 4 | start + 33 weeks | Jun 1st 2015 |