== Important Dates ==
== Important Dates ==


* Implementation Due : Start + 15 weeks
{| class="wikitable"
* Test and Fix Due : Start + 25 weeks
|-
* Demonstration Due : Start + 29 weeks
! Milestone task !! Elapsed time (weeks) !! Expected completion !! Forecast completion
* Landing Due : Start + 33 weeks
|-
| Implementation || 15 || start + 15 weeks || Jan 26th 2015
|-
| Test and fix || 10 || start + 25 weeks || Apr 6th 2015
|-
| Demonstration || 4 || start + 29 weeks || May 4th 2015
|-
| Landing || 4 || start + 33 weeks || Jun 1st 2015
|}


== Contract Products ==
== Contract Products ==

Revision as of 12:13, 14 October 2014

Overview

The goal of the CLIO Simplification Implementation contract is the implementation in the Lustre source code of the CLIO Simplification Design that resulted from Project 2 of Contract SFS-DEV-003.

For the contract statement of work, see SFS-DEV-004_SOW.pdf

Key People

OpenSFS

  • Galen Shipman - OpenSFS Contract Administrator
  • Christopher Morrone - OpenSFS Technical Representative

Project Approval Committee (PAC)

  • Christopher Morrone - PAC Chair
  • Colin Faber
  • Patrick Farrell
  • Jason Hill
  • James Simmons
  • Cory Spitz

Intel

  • Andreas Dilger - Consulting Architect
  • Jinshan Xiong - Lead Engineer

Important Dates

Milestone task Elapsed time (weeks) Expected completion Forecast completion
Implementation 15 start + 15 weeks Jan 26th 2015
Test and fix 10 start + 25 weeks Apr 6th 2015
Demonstration 4 start + 29 weeks May 4th 2015
Landing 4 start + 33 weeks Jun 1st 2015